NEH Budget and Work-plan Revision for the TEI Consortium project, Research and Demonstration, Preservation and Access, National Endowment for the Humanities
Workplan:
Year 1:
Contributed: Survey of library, scholarly, and other representative users who use TEI in SGML, collecting of samples of their work, and selection of a limited number of projects to participate in the year-two task force on SGML to XML migration.
Year 2:
4. Task Force on SGML to XML conversion of legacy TEI data, in which selected TEI experts and editors (8 people, total) work closely with representatives from projects with significant TEI SGML holdings (another 10 people) to diagnose and document the problems, methods, and tools necessary to design and effect a migration from SGML to XML, in TEI. One start-up meeting with editors and experts only; one mid-term meeting with project representatives; one final meeting with editors and experts. Participation from TEI technical writer for four months, participation of TEI editors and executive director for two months. Travel to two one-day meetings for 8 people, travel to one two-day meeting for 18 people. $67533.33
5. Specifications for software tools (including a testing suite for minimal TEI conformance) in response to results of task force. Specifications generated by TEI editors, travel to one meeting. $6548.46
Budget:
Salaries & Wages |
|
year |
month |
week |
|
|
|
Steven DeRose, Editor |
|
80000.00 |
6666.67 |
1666.67 |
|
|
|
Lou Burnard, Editor |
|
80000.00 |
6666.67 |
1666.67 |
|
|
|
Sebastian Rahtz, Consultant |
|
80000.00 |
6666.67 |
1666.67 |
|
|
|
Tone Merete Bruvik, Executive Director |
|
80000.00 |
6666.67 |
1666.67 |
|
|
|
Kirk Hartings, Consultant |
|
60000.00 |
5000.00 |
1250.00 |
|
|
|
Technical Writer |
|
60000.00 |
5000.00 |
1250.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1) Implementing ED W69 (before ACH/ALLC 2001) |
|
|
|
|
NEH |
Cost Sharing |
Total |
|
Editors, 2 weeks work |
|
|
|
1666.67 |
1666.67 |
3333.33 |
|
Travel (include. Expences) |
|
|
|
4000.00 |
|
4000.00 |
|
Subtotal |
|
|
|
5666.67 |
1666.67 |
7333.33 |
|
|
|
|
|
|
|
|
2) XSLT tools for DTD & Guidelines |
|
|
|
|
NEH |
Cost Sharing |
Total |
|
Lou Burnard, 1 month |
|
|
|
3333.33 |
3333.33 |
6666.67 |
|
Steven DeRose, non |
|
|
|
0.00 |
|
0.00 |
|
Sebastian Rahtz, 1 months |
|
|
|
6666.67 |
|
6666.67 |
|
Kirk Hastings, 1 month |
|
|
|
5000.00 |
|
5000.00 |
|
Executive Director, 1 week |
|
|
|
1666.67 |
|
1666.67 |
|
Travel (include. Expences) |
|
|
|
11595.00 |
|
11595.00 |
|
Subtotal |
|
|
|
28261.67 |
3333.33 |
31595.00 |
|
|
|
|
|
|
|
|
3) Rewriting the Guidelines |
|
|
|
|
NEH |
Cost Sharing |
Total |
|
Editors, 2 month |
|
|
|
6666.67 |
6666.67 |
13333.33 |
|
Technical Writer, 1.5 months |
|
|
|
7500.00 |
|
7500.00 |
|
Subtotal |
|
|
|
14166.67 |
6666.67 |
20833.33 |
|
|
|
|
|
|
|
|
Project managment |
|
|
|
|
|
|
|
|
Exec.dir. 1.5 months |
|
|
|
5000.00 |
5000.00 |
10000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Subtotal -
first year of the project: |
|
|
|
|
53095.00 |
16666.67 |
69761.67 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4) Task force beginning in May 2002 |
|
Travels |
Days |
|
NEH |
Cost Sharing |
Total |
|
5 independent persons, report to Tone Merete Bruvik |
|
|
|
|
|
|
|
1 startup meeting, 5 + 1 + 2 = 8 persons x 1 day |
8.00 |
8.00 |
|
|
|
|
|
1 workshop: 5 + 1
+ 2 + 10 = 18 persons x 2 day |
18.00 |
36.00 |
|
|
|
|
|
1 meeting, 5 + 1 + 2 = 8 persons x 1 day |
8.00 |
8.00 |
|
|
|
|
|
Travel: |
|
|
|
34000.00 |
|
34000.00 |
|
Expences |
|
|
|
5200.00 |
|
5200.00 |
|
Editors, 1.5 month |
|
|
|
6666.67 |
3333.33 |
10000.00 |
|
Executive Director, 1.5 month |
|
|
|
6666.67 |
3333.33 |
10000.00 |
|
Technical Writer 3 months |
|
|
|
15000.00 |
|
15000.00 |
|
Subtotal |
|
|
|
67533.33 |
6666.67 |
74200.00 |
|
|
|
|
|
|
|
|
5) Redesigning Pizza Chef |
|
|
|
|
|
|
|
|
Spec. Ediotors, 1 week |
|
|
|
1666.67 |
|
1666.67 |
|
Travel (include. Expences) |
|
|
|
4410.00 |
|
4410.00 |
|
Subtotal |
|
|
|
6076.67 |
0.00 |
6076.67 |
|
|
|
|
|
|
|
|
Project managment |
|
|
|
|
|
|
|
|
Exec.dir. 1.5 months |
|
|
|
5000.00 |
5000.00 |
10000.00 |
|
|
|
|
|
|
|
|
Subtotal -
second year of the project: |
|
|
|
|
78610.00 |
11666.67 |
90276.67 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL |
|
|
|
|
131705.00 |
28333.33 |
160038.33 |
|
|
|
|
|
|
|
|